Default Re: Early build engines to late build cars

<div class="ubbcode-block"><div class="ubbcode-header">Originally Posted By: 70 copo</div><div class="ubbcode-body">I agree.

Here are some of the Manufacturing and scheduling issues that could cause date abnormalities with drivetrain components at Norwood.

A QA/QC hold at blocks at the foundry, or at the Mfg plant. (Flint MI or Tonawanda NY)

Scheduling or logistical problems with the rail road and inclement weather (snow storm -floods-mechanical rail problems)

Railroad strikes, teamster strikes

Strikes at the foundry or the Mfg plant

Problems with Logistics and Application 35 lead time build scheduling. Errors here were miss counts and just Having enough workers to get the rail and trucks loaded and then unloaded timely and in the build system to meet the established production schedule. No bar code scanners yet it was a manual count. </div></div>

Phil,
Most of those scenarios you mention would result in an engine arriving late and holding up the scheduling of the car, rather than arriving earlier and sitting around for months before being installed in a chassis. As you know, a sequence number wasn't assigned until the inventories were checked and indicated that all the parts needed were at the plant.
Of course, by &quot;QC hold&quot; you may be referring to an engine failure at test run, requiring a rebuild and a delay which would result in an engine with an assembly date much earlier than the car assembly.

Verne [img]<<GRAEMLIN_URL>>/biggthumpup.gif[/img]